Friday, October 23, 2009

Studio C, Lounge Bar & HVAC Progress

HVAC ducts being ran through hallway





Studio C compression sub-ceiling being framed

DJ booth takes form in "Radio Room"




Shots of air conditioning/heating in the "Radio Room" & "BeatBox Pros" office.


AC/heat vent in Studio A vocal booth


Isaac filling in gaps with acoustic caulking


Construction begins on lounge area bar




Thursday, October 15, 2009

Window Adjustment & Machine Room Progress

Machine room framing is completed.


"Studio A" Vocal Booth Window Resized

Tuesday, October 13, 2009

Progress on Studio A Ceiling Joist, BeatBox Pros Show Room & Radio Room


Today the crew installed the ceiling joists into Studio A.


Below is a picture of the second layer of Studio A vocal booth wall, temporarily raised.

BeatBox Pros Show Room & Radio Room framing complete.

 

Hallway starts forming.....

Studio B vocal booth doorway being framed....

Saturday, October 10, 2009

Serious Framing Progress!

The progress continued over the weekend. The fellas came in with some serious framing in mind!

Besides the frames for our Machine Room, all framed walls went up today! It felt good being able to walk into each room and imagine what's to come. Although the framed walls are only one step of this lengthy detailed process, it sure does feel like progress is being executed! That's what counts!

Dave Hampton has been monitoring progress and development via phone and this blog. He's currently in New York at AES.


Drywall being applied to inside of Studio "A" vocal booth (first wall layer).

Drywall being applied to exterior of Studio "A".
Inside shots of Studio "A".



Looking into Studio "A" from vocal booth.

Carefully checking wall leveling.
Drywall being applied to exterior of "Studio" A (entrance side).


Ceiling joists being cut to size.

Looking down hallway past Studio "A", towards Radio Production Room.

Installation of partitioning wall between Radio Production Room & BeatBox Pros Showroom.
Radio Production Room
BeatBox Pros Showroom
Ceiling joists installed in Studio "A".

First layer of exterior drywall on Studio "A".

The boys called it a day after some serious progress. Time to go home to the family, throw down some carne asada and a couple cold ones. Back to business as usual on Monday!




Friday, October 9, 2009

Studio "A" Takes Shape!

Today, the crew came in and began preparing the floor for specialty material that will be laid down, prior to erecting Studio "A" walls.

Once the glue was spread and material was laid out, the walls were raised and anchored to the concrete.


Cleaning and preparing floor for glue application.

Glue being spread.

Specialty material being laid out.



Carefully monitoring position of material.



Most of Studio "A" control room space covered with specialty material.
Studio "A" walls start going up.

The crew picks up a 14 foot wall and begin moving towards final anchor position.

Three walls of Studio "A" are up.
Isaac and Jim posing for a quick Kodak moment.
The crew moves a couple of walls around to access final Studio "A" wall.


Last Studio "A" wall (layer 1 of partition between control room and vocal booth) is positioned.
Crew anchors last wall and calls it a day.
Studio "A" looking nice and spacious!